8 workers can finish a job in 15 days. How many days will 12 workers need, working at the same rate?

Correct answer: B. 10 days

The job takes 8 × 15 = 120 worker-days. With 12 workers it takes 120 ÷ 12 = 10 days. More workers means fewer days, so this is an inverse proportion.

medium

Answer and explanation

The correct answer is B. 10 days

The job takes 8 × 15 = 120 worker-days. With 12 workers it takes 120 ÷ 12 = 10 days. More workers means fewer days, so this is an inverse proportion.

Topic: Numerical Word Problems MCQs · Subject: Numerical Ability