6 workers can finish a road repair in 10 days. How many days will 15 workers take at the same rate?
Correct answer: B. 4 days
The job needs 6 × 10 = 60 worker-days. With 15 workers it takes 60 ÷ 15 = 4 days. This is inverse proportion: more workers, fewer days.